Sacramento River Erosion Contract 3
Title:  

Sacramento River Erosion Contract 3

Agency:  

U.S. Department Of Defense

State:  

California

NAICS Code:  

237990

Industry:  

Construction

Solicitation Type:  

Request for Information

Solicitation ID:  

W9123825S0021

Open Date:  

8/18/2025

Questions Due Date:  

9/18/2025

Close Date:  

9/18/2025

Projected Award Date:  

2/1/2026

Project Duration:  

670 days

Last Updated:  

8/21/2025

Description:
The United States Army Corps of Engineers (USACE) Sacramento District (SPK) is seeking information from small business firms for a potential government requirement related to flood risk reduction work along the Sacramento River. The project involves protecting in-place vegetation, existing facilities, and structures, as well as earthwork, import of rock materials, construction of stone protection, and other related work. The potential requirement may result in a firm-fixed-price solicitation issued in November 2025, with an estimated construction duration of 670 calendar days. • The project is located in Sacramento, California, and involves work along the Sacramento River. • The project requires a firm-fixed-price contract with an estimated construction duration of 670 calendar days. • The government estimates the magnitude of construction for the potential project to be between $25,000,000 and $100,000,000. • The NAICS code for the potential requirement is 237990, Other Heavy and Civil Engineering. • The small business size standard for the NAICS is $45,500,000 annual revenue.
Attached Files:

Please visit the bid source via the “Link to Bid Source” button below for documentation.

Contact Information:

Julie Maxwell(Contract Specialist)

julie.maxwell@usace.army.mil

(916) 557-7989

Budget Estimate (AI):

$25,000,000 – $100,000,000

Based on the document, the government estimates the magnitude of construction for the potential project to be between $25,000,000 and $100,000,000. This estimate is likely influenced by the scope of work, which includes flood risk reduction work along the Sacramento River, and the estimated construction duration of 670 calendar days. The actual budget may vary depending on various factors, such as the complexity of the project, the number of bidders, and the final contract terms.

Similar Opportunities provided by Bid Banana AI

The Bid Lab’s Experts Are Ready To Help You Win RFPs

The Bid Lab is the only RFP consulting firm of its kind, specializing in guiding small and medium-sized businesses through the proposal response process. We have RFP experts ready to help you respond to that perfect opportunity you discover in Bid Banana.

  • Trusted by 100s of small business owners
  • Experience working on 1000s of RFP responses
  • Success stories in virtually every industry you can check out by clicking here.