1. Project Overview
The project consists of furnishing all labor, materials, equipment, and services necessary to install three groundwater monitoring wells within the boundaries of Watkins Glen State Park for water-level and quality monitoring purposes. The wells will support a multi-year groundwater monitoring program led by the United States Geological Survey (USGS).
The exact well locations within the park boundary are to be located within the zones identified in Attachment A. OPRHP recommends a site visit to fully understand the current terrain and access constraints, which will determine suitable drilling equipment.
The contractor shall complete the installation in accordance with:
· USGS groundwater monitoring well specifications (provided)
· Applicable state environmental regulations
· Best practices for hydrogeological drilling and monitoring well construction
· State Park environmental protection requirements
The contractor will not install water quality monitoring instruments; USGS personnel will install them after the well is completed.
2. Contractor Responsibilities
The contractor shall provide:
· Qualified drilling contractor and qualified personnel
· All drilling rigs and specialized equipment required for environmental well installation
· Materials for monitoring wells (casing, screen, filter pack, grout, protective casings, locking caps, etc.)
· Site access coordination
· Temporary erosion and sediment control measures
· Well development and documentation
· Soil samples and complete log of borehole, including sediment types encountered, soil moisture, and completion information
· Restoration of disturbed areas
3. Pre-Construction Activities
3.1 Project Coordination
The contractor shall coordinate with:
· United States Geological Survey project staff
· NYS Parks management staff
· NYS Department of Environmental Conservation (if required)
Coordination activities include:
· Pre-construction meeting
· Final confirmation of well locations
· Site access planning
· Environmental protection measures
3.2 Site Investigation and Layout
The contractor shall:
· Review the project map and site conditions
· Conduct a site walk with USGS and NYS Parks representatives
· Stake the final well locations as directed by USGS and OPRHP staff
· Confirm that drilling locations avoid:
o Park utilities
o Sensitive habitats
Utility clearance shall be performed through consultation with NYS Parks management staff DigSafeNY.
3.3 Permitting
The contractor shall obtain any necessary permits required for:
· drilling activities in NYS
temporary access to NYS Park lands
All work must comply with state groundwater well regulations.
4. Access and Site Preparation
4.1 Site Access
Because the work occurs inside a state park, the contractor must minimize environmental disturbance.
Work may require:
· low-impact drilling rigs
· matting or temporary access surfaces
· hand-clearing of small vegetation
No tree or shrub removal where d.b.h. > 3” shall occur without written approval.
4.2 Erosion and Sediment Control
The contractor shall install appropriate erosion and sediment control (ESC) measures, which may include:
· silt fencing
· stabilized entrances
· erosion control matting
· temporary drainage diversion
· temporary safety fencing to keep the public away from the drilling rig and associated equipment
ESC measures must comply with state stormwater management standards and remain in place until final site restoration.
5. Monitoring Well Installation
5.1 Drilling Method
The contractor shall use an environmentally appropriate drilling method, such as hollow-stem auguring.
The final method must meet USGS monitoring well installation standards.
The contractor must decontaminate all drilling equipment between wells to prevent cross-contamination.
5.2 Borehole Construction
The contractor shall drill a dual completion well with two separated zones (overburden zone and bedrock zone). Within the bedrock zone, there will be an additional 5 ft into rock, with a screened interval at the base of the glacial sediment interval.
Required well depths are currently estimated at around 65 feet within Zone A and in the range of 35 to 70 feet within Zone B, depending on final placement. Please see attachment A for zone locations.
During drilling, the contractor shall:
· Maintain borehole stability
· Log soil and geologic conditions
· Collect soil samples if requested by USGS
· Document groundwater encounter depths
5.3 Well Construction
Each monitoring well shall include:
· Schedule 40 PVC casing or other USGS-approved casing material
· Factory slotted well screen
· Filter pack (clean silica sand), extending at least 2 ft above the well screen
· Bentonite seal
· Cement of bentonite grout seal to the ground surface
Typical components:
· 6-inch diameter well casing
· Screen length TBD based on depth to top of bedrock (anticipated depths of 40-60 ft)
· Screen slot size based on formation grain size
Final design to be confirmed by contractor with USGS and OPRHP.
5.4 Surface Completion
Each well shall be completed with:
· Protective steel casing
· Locking well cap (USGS will provide locks)
· Flush-mounted or stick-up well completion, depending on park conditions
· Concrete pad around well casing
· Protective bollards if necessary
Surface completion must protect the well from:
· Vandalism
· Wildlife
· Surface runoff infiltration
6. Well Development
After installation, the contractor shall develop the well to remove drilling fines and establish hydraulic connectivity with the formation.
Acceptable development methods include:
· surging
· pumping
· air lifting bailers
Development shall continue until:
· turbidity stabilizes or
· water runs clear or
· parameters meet USGS requirements
7. Remote Access Considerations
Due to the location within Watkins Glen State Park, wells may be located in areas with limited vehicle access.
The contractor shall provide equipment capable of operating in such environments, which may include:
· track-mounted drilling rigs
· small footprint drilling equipment
· off-road transport vehicles
· temporary ground protection mats
8. Decontamination Procedures
All drilling equipment, tools, and sampling devices shall be decontaminated between wells using approved methods such as:
· potable water rinse
· distilled water rinse
Wastewater generated during decontamination must be properly contained and disposed of.
9. Waste Management
Drilling waste may include:
· drill cuttings
· drilling fluids
· purge water
The contractor shall:
· Temporarily contain materials on-site
· Dispose of waste in accordance with state environmental regulations.
10. Site Restoration
After completing well installation, the contractor shall restore disturbed areas to pre-construction conditions.
Restoration activities include:
· removal of erosion control devices once the site is stable
· regrading of disturbed soil
· reseeding with approved native vegetation
· removal of all drilling debris
11. Deliverables
The contractor shall submit the following documentation:
· Drilling logs
· Depth to groundwater
· Well construction diagrams
· Well development records
· Materials used
· Photographs of completed wells
Erosion control documentation
All records shall be submitted to NYS Parks within 30 days of project completion.
12. Monitoring Equipment Installation
Installation of water-level monitoring instrumentation will be completed by personnel from USGS after well installation is complete. The contractor shall ensure wells are secured prior to instrument installation.
13. Health and Safety
The contractor must comply with all applicable safety regulations, including:
· OSHA standards
· Drilling safety protocols
· Environmental hazard prevention (and spill kit present)
· Coordination with park management regarding park visitor safety considerations.
Business enterprises awarded an identical or substantially similar procurement contract within the past five years:
none