Lee County, Florida is seeking a qualified contractor to construct site improvements and install two ChargePoint electric bus chargers at the LeeTran Headquarters (3401 Metro Parkway, Fort Myers). The scope includes demolition, excavation, trenching, concrete pads, protective bollards, pavement restoration and markings, erosion and sediment controls, and all associated civil works needed to support the chargers. The project is funded partially or wholly by the Federal Transit Administration, so all bidders must comply with 2 CFR part 200 federal grant requirements. Bids must be submitted electronically via IonWave or hand‑delivered by the close date, and a non‑mandatory pre‑bid meeting is scheduled for 10 Oct 2026. The contract will be awarded to the lowest responsive and responsible bidder.
• Location: LeeTran Headquarters, Fort Myers, FL
• Work: demolition, excavation, trenching, concrete equipment pads, bollards, pavement work, erosion control, and installation of two EV bus chargers
• Funding: Federal Transit Administration (FTA) – federal grant compliance required
• Submission: sealed bids via IonWave or hand‑delivery by 02:30 PM ET on 3 Nov 2026
• Pre‑bid meeting: 8 Oct 2026 (non‑mandatory)
• Required attachments: Sunbiz registration, bid bond, various certifications, and compliance forms