The Washington Suburban Sanitary Commission (WSSC) is seeking a qualified contractor to demolish and permanently abandon eight existing surge tanks at the Anacostia II Wastewater Pumping Station, including removal of trees, pavement, curbâandâgutter, associated equipment, and hazardous leadâbased paint mitigation, followed by site restoration and erosion control. The contract is awarded through a competitive sealedâbid process, with a mandatory site visit and a substantial completion schedule of 503 days.
⢠Scope: Demolition of 8 surge tanks, leadâpaint abatement, removal of 4 trees, demolition/disposal of pavement, curb & gutter, equipment, and site restoration.
⢠Location: Capitol Heights, MD (4200 Andalusia Lane) and Hyattsville, MD (preâbid meeting).
⢠Mandatory site visit on September 2, 2026 (12:00 pm).
⢠Preâbid meeting (optional) on September 2, 2026 (11:00 am).
⢠Questions due by September 16, 2026 (2:00 pm).
⢠Bid submission deadline September 30, 2026 (2:00 pm) via WSSC eâprocurement portal.
⢠Contractor must hold a Maryland state construction license with âĽ8 years experience and demonstrate $3 M+ project experience, including hazardous material removal.
⢠Required personnel: Project Manager, Scheduler, Superintendent, safety representative, and proof of safety record (EMR/TRIR).
⢠Substantial completion period: 503 days; liquidated damages $3,142 per day.
⢠Bonds, insurance, prevailingâwage, and MBE/SLBE compliance required.