Description
The project involves maintenance dredging of Tampa Harbor, including turbidity monitoring, sea turtle trawling and relocation, bird monitoring, and environmental species monitoring. The contractor will be required to commence work within 60 calendar days after receiving the Notice to Proceed and complete the work within 210 calendar days. The estimated magnitude of construction is between $10,000,000 and $25,000,000.
• The project requires Coast Guard Certified dredge equipment.
• The contractor must dispose of dredged material in DMPF-2D.
• The project includes a 1-foot allowable overdepth.
• Liquidated damages will be $1,973 per day for delays.
• A bid guarantee of 20% of the bid price or $3,000,000 is required.
• Payment and performance bonds equal to the total bid price must be submitted within 10 days of contract award.