This solicitation seeks a contractor to replace a municipal sewer line identified as Project Unit F in Montana. The work will involve removal of existing pipe, installation of new sewer conduit, and associated site restoration. Bids were received from two firms, with the lowest total bid $334,400 (after modification) and the next $378,500. A 10 % bid bond is required, and two addenda have been issued. The bid opening is scheduled for 13 Feb 2025.
• Scope: Full replacement of a designated sewer line (excavation, pipe installation, testing, backfill).
• Budget: Highest bid $378,500; contract likely under $400k.
• Requirements: 10 % bid bond, compliance with addenda 1 & 2, submission prior to bid opening.
• Contacts: Coneer Engineering (design consultant) for technical queries; procurement through the State of Montana Department of Administration.
• Competition: Two bidders (TW Ridley and Northcon Inc.) indicating a competitive but limited field.