Description
The City of Bryan is seeking qualified contractors to relocate and install water utility lines along SH‑6 at two locations: the Highpoint Drive/Briarcrest Drive intersection and the Old Reliance Road overpass. The scope includes demolition of existing waterlines, installation of new 12‑inch and 24‑inch waterlines with associated casings, grout filling, traffic and erosion control, and full testing and documentation. The estimated construction budget is $700,000 and the work is expected to begin early January 2027 with a targeted completion in late March 2027 (approximately 60 working days). Bidders must submit a competitive sealed proposal, a 5 % bid bond, and provide required insurance and performance bonds. The City will evaluate proposals based on cost (50 %), schedule (20 %), personnel experience (15 %), reputation (10 %), and proximity (5 %).
• Project locations: Highpoint Drive & Briarcrest Drive; Old Reliance Road overpass SH‑6.
• Scope: demolition of existing waterlines, install ~164 LF of 12″ waterline, 141 LF of 20″ casing, 41 LF of 24″ waterline, 298 LF of 36″ casing, grout fills, traffic/erosion control, testing, O&M manuals.
• Estimated budget: $700,000 (inclusive of all costs).
• Schedule: Notice to Proceed ≈ Jan 4 2027; Targeted Completion ≈ Mar 26 2027 (≈ 60 working days).
• Mandatory pre‑proposal meeting: Oct 1 2026 (non‑mandatory).
• Submission deadline: Oct 12 2026 3:00 PM CST (electronic or sealed).
• Required bonds: 5 % bid bond, performance and payment bonds after award.
• Evaluation criteria: cost, schedule, key personnel, past performance, proximity.
• Contractor must be registered with the City’s Contractor Registration Program (score ≥70).
Attached files
The solicitation documents live at the source — open the bid source above to download them.