The Alaska Energy Authority (AEA) is seeking bids to purchase and deliver long‑lead electrical equipment—including conductors, fiber optic cable, switchgear, and fiberglass elbows—to support the Bradley Lake 3‑phase power upgrade. The contract is a single‑source procurement of commodities with delivery required by April 1 2027. Bidders must be licensed in Alaska, submit a firm, unconditional offer by September 11 2026, and provide all required certifications and insurance. The award value is estimated between $2 M and $3 M, with the contractor responsible for shipping to the project site in Homer and coordinating with AEA project managers.
• Scope: purchase and delivery of specified power‑line components (conductor, fiber, switchgear, elbows).
• Delivery: final destination in Homer, AK; all items to arrive by April 1 2027.
• Bid submission: electronic or hard‑copy by 1:00 PM on September 11 2026; no pre‑bid conference.
• Requirements: Alaska business license, insurance (CGL $300k, workers’ comp, auto), debarment and lobbying certifications.
• Budget: $2‑3 million; contract term runs from award until final acceptance of delivered goods.