The Macon Water Authority is seeking sealed bids for the complete supply, installation, and laser‑alignment of two 1000 HP vertical turbine motors at the Amerson Water Treatment Plant reservoir pump station. The contract includes provision of a crane, roof removal, motor removal and storage, vibration detection systems, new couplings, full electrical disconnections/reconnections, and post‑installation vibration analysis. Fifty‑one percent of the work must be self‑performed, and the contract is awarded on a lump‑sum basis after a mandatory pre‑bid conference.
• Scope: Furnish all labor, materials, tools, equipment, and appurtenances for two 1000 HP turbine replacements.
• Mandatory pre‑bid meeting: Nov 3, 2026, 10:00 AM, Amerson Water Treatment Plant (GA).
• Bid submission deadline: Nov 17, 2026, 2:00 PM ET, Macon Water Authority, 537 Hemlock St., Doroth Black Training Room.
• Questions due: Nov 9, 2026, 10:00 AM.
• Contract duration: 180 consecutive calendar days.
• Performance & payment bonds required (100 % of contract price).
• Minimum 51 % of work must be self‑performed.
• Local business participation encouraged; minority‑owned subcontractor tax credits available.