The City of San Francisco is soliciting a qualified Micro‑LBE (Certified Small Business) to repair and reconstruct the walking pathways within Alta Plaza Park. The work includes demolition of existing asphalt, installation of geotextile and aggregate base, pour of new concrete pathways (4‑6 in. thick) with reinforcement, jointing, slope control, and restoration of adjacent turf. The contract is set‑aside for Micro‑LBEs, requires a California “A” or “C‑8” contractor license, a minimum 25 % self‑performance, and compliance with prevailing‑wage, safety, and waste‑diversion regulations. The estimated project cost is $851,800, with a total schedule of 60 days to substantial completion and an additional 14 days to final completion.
• Scope: Demolition, base preparation, concrete placement, joint cutting, turf reinstatement, and site cleanup.
• Eligibility: CMD‑certified Micro‑LBE, “A” or “C‑8” license, self‑perform ≥ 25 % of contract value, DIR‑registered, and meeting City safety‑pre‑qualification.
• Schedule: Bids due Nov 19, 2026; work to be completed within ~74 days from Notice to Proceed.
• Financials: Estimated contract value $851,800; 5 % retention; 100 % performance & payment bonds required.
• Compliance: Prevailing‑wage (OLSE) reporting, GreenHalo waste‑diversion (≥ 75 % landfill diversion), and required insurance.