Awarded vendors
- R&M Engineering – Ketchikan
Description
The City & Borough of Wrangell awarded a professional surveying contract to re‑plat six parcels within the Wrangell Industrial Park. The work includes a control survey, as‑built survey, installation of new boundary monuments, and preparation of preliminary and final plats in both hard‑copy and electronic formats, all to be completed within 30 days of award. The contract is a fixed‑price lump‑sum award to R&M Engineering – Ketchikan, with milestone payments tied to deliverables and a $100 per day penalty for delays.
• Scope: control & as‑built surveys, monument installation, preliminary & final plat preparation (paper, Mylar, AutoCAD, PDF).
• Schedule: proposals due Aug 21 2012; work must finish 30 days after award; penalties for overruns.
• Payment: up to 50 % after preliminary plat, up to 75 % after final plat approval, 100 % after recording; net‑30 terms.