This solicitation is a limited‑remodel of the 2nd‑floor of the Benton County Health Department Center, covering roughly 2,800 sf. The work includes demolition of existing interior elements, construction of new interior partitions, installation of new doors, millwork, windows, lighting, and HVAC adjustments, as well as routing of data cabling. The County will handle fire‑sprinkler and alarm work, but any required relocations must be reflected in the GC’s bid. A 10 % contingency is required. The estimated construction budget is $178,000, with a six‑week construction schedule (Oct 21 – Dec 2 2025). Bids were due 30 Sep 2025, and the contract is reported as awarded to Milestone Construction.
• Scope: interior demolition, new walls, flooring, ceilings, doors, millwork, lighting, HVAC adjustments, data runs.
• Budget: $178 k with a mandatory 10 % contingency.
• Schedule: 6 weeks construction, start 21 Oct 2025, completion 2 Dec 2025.