Description
The Municipality of Skagway is replacing its small‑boat harbor lift station. The project involves complete demolition of the existing lift‑station structure, installation of a new wet‑well and valve‑vault, associated sanitary‑sewer pipe and conduit, extensive earthwork, concrete paving and curb/ gutter work, and full electrical and control system installation. The work must be completed in two phases: demolition and primary construction by 15 Nov 2020 and final close‑out by 1 Apr 2021. The contract is a unit‑price, prevailing‑wage agreement with strict liquidated‑damage penalties ($1,000/day) for schedule overruns, and requires extensive submittals (erosion‑control plan, de‑watering plan, permits, insurance, bonds, and certified payroll). The bid package was due 25 Sep 2020, with a mandatory pre‑bid meeting on 17 Sep 2020. No vendor was identified in the public records.
• Scope: demolition, wet‑well/valve‑vault construction, sewer pipe & conduit, concrete paving, electrical/control systems.
• Schedule: Primary work by 15 Nov 2020; final completion by 1 Apr 2021.
• Procurement: Unit‑price contract, open competition, Davis‑Bacon wage reporting required (> $25k).