Description
The contract involves the construction of a storm water diversion from the Hawthorne Irrigation Ditch to the existing storm water system. The project includes the construction of new 36" storm sewer pipe, regrading of a drainage channel, and a water main lowering near the intersection of Highway 44 and Elk Vale Road. The engineer's estimate for the project is $262,000.00, and the advertising authority is $300,000.00. The bid results show two vendors, RCS and Precision Grading, with base bids of $349,090.52 and $344,788.98, respectively. Key aspects of the contract include:
• Storm water diversion construction
• New 36" storm sewer pipe installation
• Drainage channel regrading
• Water main lowering
• Intersection of Highway 44 and Elk Vale Road
• Engineer's estimate: $262,000.00
• Advertising authority: $300,000.00