Awarded vendors
- HME Construction, Inc.
Description
The contract is for the removal of in-water pilings and a pedestrian ramp at the west side of Sellwood Bridge in Portland. All site access is to be from water. The project is funded by Multnomah County and is subject to Oregon Prevailing Wage requirements. The contract was awarded to HME Construction, Inc. for a total bid amount of $44,107.00.
• The project involves marine construction services, including bridge construction and repair.
• The Engineer's Estimate for the project was between $60,000 and $100,000.
• The contract was awarded through a competitive bidding process, with multiple bidders submitting proposals.
• The project is expected to be completed within a certain timeframe, although the exact duration is not specified.