Awarded vendors
- Miller Trucking & Excavating
Description
The City of Galesburg awarded a design‑build contract for the drainage‑system installation on the Bunker Links Golf Course (Phase II). Miller Trucking & Excavating will install drainage across multiple holes, with a total contract value of just over $300 K and a tight 35‑day construction window. The work will begin in early October and finish by the end of December 2026, following a standard competitive bid process.
• Scope: Design‑build installation of golf‑course drainage for specific holes (1, 2, 8, 9, 13, 14, 18).
• Value: $301,721 total, paid as a lump‑sum award.
• Timeline: Start Oct 1 2026, complete Dec 31 2026 (35 calendar days of actual work).
• Vendor: Miller Trucking & Excavating (Silvis, IL) – sole awardee.
• Procurement: Full and open competition, bid tabulated July 8 2026.