Description
This contract concerns the replacement of two (with an optional third) heating‑water boilers at the central plant of the Snohomish County jail. The procurement was limited to pre‑qualified “Small Works” vendors and required a mandatory site visit on October 9, 2018. Five vendors submitted fixed‑price bids for the boiler equipment (Hydrotherm KN‑20) and associated hardware, with total bid amounts (including a 9.7 % sales tax) ranging from roughly $142 k to $212 k for the primary line item and $76 k to $100 k for the boiler itself. No award was indicated in the bid tab, leaving the contract’s award status unresolved.
• Scope: Replace two boilers (base) with an optional third (alternate); primary equipment model Hydrotherm KN‑20.
• Procurement: Small‑Works roster, limited competition, mandatory pre‑bid site visit at 3025 Oakes Ave, Everett, WA.
• Financials: Combined vendor totals ≈ $1.3 M (including tax); individual bids span $142‑$212 k for ancillary items and $76‑$100 k for the boiler.