The Bethel School District is seeking a single‑contractor to design‑build a new pre‑engineered metal building (≈10,500 SF) to house transportation and nutrition services, plus extensive site improvements such as new entry access, asphalt paving, a storm‑water garden, parking, a bus wash canopy, and a trash enclosure. The project must comply with 2025 Oregon Building and Energy Codes, include full fire‑sprinkler systems, meet ADA requirements, and satisfy seismic design criteria for zones 3‑4. All work is to be performed under a competitive sealed‑bid IFB, with mandatory pre‑bid site tour and strict submission deadlines.
• New 10,500 SF pre‑engineered metal building with interior bays, restrooms, lounge, and walk‑in freezers.
• Site work: grading, utilities, new access, asphalt parking, storm‑water garden, concrete plaza, bus wash and trash enclosure.
• Full MEP (HVAC, plumbing, fire‑sprinkler), electrical, fire‑protection, and specialty equipment installations, adhering to Oregon codes and ASHRAE 90.1‑2019.
• Mandatory site tour 9 Sep 2026; bid submission 20 Oct 2026; substantial completion required by 1 Oct 2027.