The GSA Public Buildings Service is soliciting a qualified construction contractor to build the new Gate 7 multi‑level parking garage and associated site improvements at the St. Elizabeths West Campus in Southeast Washington, DC. The award will be a single firm‑fixed‑price contract covering all construction activities, from site work and utility relocation to structural framing, mechanical ventilation, façade, security systems, and final close‑out documentation. The project is valued between $120 M and $160 M and will be executed in a two‑phase, design‑bid‑build process with a mandatory pre‑proposal conference (Oct 5 2026) and Phase 1 technical proposals due Oct 26 2026. Phase 2 will include full price and technical proposals, a bid bond, and a required Project Labor Agreement. Work must be coordinated with an active high‑security federal campus, historic‑preservation constraints, and multiple D.C. agencies.
• Scope: full new construction of a multi‑story parking garage (foundations, slabs, structural steel, parking decks, elevators, ventilation, fire‑life‑safety, IT, security, landscaping, storm‑water, historic façade).
• Location: St. Elizabeths West Campus, SE Washington, DC (federal/high‑security site).
• Estimated contract value: $120‑$160 M.
• Delivery method: Two‑phase Design‑Bid‑Build; Phase 1 (technical qualification) → Phase 2 (price & full technical).
• Key dates: Pre‑proposal conference Oct 5 2026; Questions due Oct 8 2026; Phase 1 offer deadline Oct 26 2026; Phase 2 deadline TBD.
• Mandatory requirements: bid bond (Phase 2), Project Labor Agreement, security clearance for all personnel, compliance with GSA 2026 PBS Core Building Standards, historic preservation, and DEI clauses.
• Evaluation: 25 % safety record, 25 % relevant experience, 25 % key personnel, 25 % past performance (Phase 1); Phase 2 adds technical approach, schedule, quality/safety, and small‑business participation.