The City of Hollywood is soliciting bids for a maintenance contract to replace packing media and perform comprehensive servicing on three degasifier units (2, 3, and 4) at its water treatment plant. Work includes power‑washing vessel interiors, repairing components, installing new media support grids and differential pressure gauges, disinfecting vessels, and resealing access doors, all while keeping the remaining units operational. The contract will be awarded to the lowest responsive and responsible bidder and will run for 210 calendar days from the award date.
• Scope: Packing media replacement, power washing, repairs, gauge replacement, vessel disinfection, door resealing for three degasifiers.
• Location: City of Hollywood Water Treatment Plant, 3441 Hollywood Blvd, Hollywood, FL 33021.
• Contract Method: Single prime contract; work performed one unit at a time.
• Schedule: IFB issued Sep 9 2026; pre‑bid meeting Sep 23 2026 (non‑mandatory); questions due Sep 29 2026; bid deadline Oct 14 2026, 3 PM.
• Duration: 210 days contract period, with possible 120‑day extension.
• Mandatory Requirements: 5 % bid bond, performance and payment bonds, insurance (general liability, auto, workers’ comp, pollution), and compliance with local, state, and federal regulations.
• Evaluation: Lowest price among responsive, responsible bidders; tie‑breaker criteria include drug‑free workplace, local vendor preference, proximity, and minority‑owned status.
• Contact: Juan Figueroa, Senior Project Manager (