Description
The Bureau of Land Management (BLM) is soliciting quotes for the removal and replacement of three existing iron filtration units, replacement of exhausted filter media, rehabilitation of associated treatment components, and reactivation of the system to restore proper operation of the drinking water facility at Pompey's Pillar in Montana. The project requires the replacement of two hydropneumatic tanks and the removal and disposal of liquid waste generated under the contract. The contractor must assume that offsite disposal at an appropriately licensed facility is required and include all associated costs in their proposal.
* The project location is within Yellowstone County, Montana.
* The work location is 3039 Highway 312, Pompey's Pillar, MT 59064.
* The average water demand of the system is 1300 gallons per day with a maximum demand of 6000 gallons per day.
* The system supplies the Pompey's Pillar Interpretive Center.
* The existing pump is a Goulds 33GS20 with an Aquavara AVII Variable speed pump controller.
* The well has a total depth of 33 feet with a static water level of 4.5 feet.