The State of North Carolina, via Southwestern Community College, is seeking a qualified contractor to replace and upgrade the hot‑water distribution system in the Founders Hall building. The work is a turnkey project that includes demolition of the existing electric tanked water heater, installation of four Navien NPE‑240A2 tankless water heaters, upgrades to the recirculation system, insulation of all hot‑ and cold‑water piping, and necessary permitting, inspections, and warranty support. Work must be coordinated around college class schedules, with a brief 1‑2 day service interruption, and must begin within 30 business days of contract award. A mandatory pre‑bid site visit is required. Bids are due November 12, 2026.
• Remove existing electric tanked water heater
• Install four Navien NPE‑240A2 tankless units in boiler room
• Upgrade recirculation system (internal pumps, external loop)
• Insulate all hot‑ and cold‑water piping in conditioned spaces
• Provide all permits, inspection coordination, and warranty (8 yr heat exchanger, 5 yr parts, 1 yr labor)
• Maintain kitchen operation during installation; ensure redundancy so any single unit failure does not interrupt service
• Deliver design submittals, progress reports, as‑built documentation, and final commissioning
• Mandatory site visit on 28 Oct 2026; questions due 4 Nov 2026; bid opening 12 Nov 2026.