This solicitation invites sealed bids for the design‑build construction of Phase II of Cassville White Road widening, including the relocation of water and sanitary sewer utilities in Bartow County, Georgia. The contractor must supply all materials, labor, equipment, and incidentals to install new water mains (12”, 8”, 6”) and HDPE sanitary sewer force main, along with associated steel casings, within a maximum of 100 days for substantial completion and up to 480 days for full contract close‑out. Plans are available for purchase, and bidders must provide performance and payment bonds, a 5 % bid bond, and comply with Georgia law and E‑Verify requirements.
• Scope: Road widening, water main installation (12”, 8”, 6” DIP), 3” HDPE sanitary sewer force main, steel casings (12”, 20”).
• Total linear footage: approx. 1,500 LF water main, 1,500 LF sewer and casings.
• Contract type: Single‑award, sealed bid, “pay‑when‑paid” with required bonds.
• Schedule: Start after award; 100 days for substantial completion, 450 days for final completion, 480 days for close‑out.
• Bid submission: By 3:00 PM ET, Nov 10 2026 at Bartow County Administration Building.
• Pre‑bid questions due: Nov 3 2026, Noon (local time).
• Required documents: Bid form, cashier’s check or certified check, bid bond, E‑Verify affidavit, performance/payment bonds.