The Johnson County Park & Recreation District (JCPRD) is seeking a multi‑disciplinary design team to provide architectural, landscape‑architectural, civil engineering, and surveying services for Phase 1 of Camp Branch Park in unincorporated Johnson County, Kansas. The scope includes updating the master‑plan graphic, site‑plan and zoning applications, utility extensions, roadway and trail design, parking lot and lighting design, prefabricated restroom building design, storm‑water treatment, habitat restoration, and coordination with utility providers and permitting agencies. The consultant must be Kansas‑licensed, attend a mandatory on‑site visit on Oct 1, 2026, and submit a full electronic proposal by Oct 15, 2026. Interviews are scheduled for Nov 3, 2026, with award expected after Board approval on Nov 18, 2026. The design effort is slated to begin Dec 2026, with construction anticipated fall 2027‑summer 2028.
• Mandatory pre‑proposal site visit (Oct 1, 2026) – rain‑or‑shine.
• Required Kansas professional licensure before contract execution.
• Scope covers roadway, parking, trails, utilities, restroom building, lighting, storm‑water, and habitat restoration.
• Coordination with Evergy (power), WaterOne (water), JOCO planning, codes, and environmental agencies.
• Estimated professional services budget: $6.5 M.
• Design‑bid‑build delivery; contract term ~12 months post‑substantial completion.