This contract awards Roncelli, Inc. a Construction‑Management (CM) services agreement for the renovation and MRI installation at Wayne State University’s Applebaum building. The CM is responsible for pre‑construction services, development of a Guaranteed Maximum Price (GMP), on‑site construction administration, and close‑out documentation, all within a Construction Cost Limitation (CCL) of $1.75 M. The scope includes relocating existing NMR equipment, constructing a new 1.5 T MRI suite with RF shielding, associated support spaces, a student lounge renovation, and full MEP, fire‑life‑safety, and interior‑finish upgrades. The project must commence by early December 2023 and achieve substantial completion by late April 2024.
• Mandatory pre‑bid meeting held 10 Nov 2023; only attendees may submit proposals.
• Bid deadline 28 Nov 2023, award announced 11 Dec 2023; work start 11 Dec 2023, final completion 26 Apr 2024.
• CM services funded under a $1.75 M cost ceiling; vendor must comply with Wayne State wage rates, insurance minimums, and certified‑payroll requirements.