This contract involves the design‑build installation of a fiber‑optic and copper premise distribution system at the Plamann Park Swimming Lake House in Appleton, WI. The county issued a sealed‑bid solicitation (IT PLF24) for a lump‑sum price, received three bids, and awarded the contract to Faith Technologies for $45,420. The scope includes installing Panduit‑certified 12‑fiber optic cable, Category‑6 copper cabling, conduit, hand‑holes, test stations, grounding, and all associated testing, labeling, and as‑built documentation. The work must be completed by May 31, 2024, with liquidated damages of $250 per day for lateness, and must meet the county’s insurance, safety, and technical standards.
• Competitive sealed‑bid process (bid deadline 27 Mar 2024)
• Lump‑sum award to Faith Technologies ($45,420)
• Scope: full premise‑distribution system – fiber, copper, conduit, hand‑holes, test stations, testing, labeling, as‑built drawings
• Completion deadline 31 May 2024 with $250/day liquidated‑damage penalty
• Requires Panduit certification, compliance with NEC/EIA‑TIA, and County insurance requirements (Attachment A)