This contract is for the City of Prescott to engage a professional engineering firm to provide complete design services for centralizing the Arizona Water Resources Department (AWRF) solids‑handling facility. The scope includes utility relocation, geotechnical investigation, topographic and ROW surveying, environmental permitting, phased construction planning, and post‑design construction support such as RFI handling and as‑built documentation. The award was made to Water Works Engineers, LLC after a competitive qualifications‑based selection process. Key points:
• Design services cover conceptual through final construction‑ready plans for a new building, two de‑watering units, and a 1‑1.5 M‑gallon solids‑holding tank.
• Deliverables include surveys, utility potholing, geotechnical reports, phased construction plans, and engineer’s certification of completion.
• The schedule spans from award (Sept 2024) to final design completion (Nov 2025) with construction slated to begin Mar 2026.