This sole‑source contract tasks SWC Telesolutions (Ethos Broadband) with the complete engineering design, permitting, construction, and operational rollout of a fiber‑optic backbone linking Elephant Butte to the Spaceport America complex. The work includes aerial and buried fiber installation, use of an exclusive pole‑attachment agreement, and delivery of a network capable of up to 10 Gbps. The contract is valued at roughly $500 K and must be finished by the end of 2026.
• Scope: detailed design, right‑of‑way acquisition, construction (≈ 4.25 mi aerial, 0.25 mi buried, 2.25 mi existing conduit), and ongoing operations/maintenance.
• Unique factors: proprietary SWC engineering staff, exclusive pole‑attachment with Sierra Electric Cooperative, and a grant‑match funding structure (25 % agency contribution).
• Timeline: 6‑month performance period (May 15 2026 – Nov 30 2026) with a hard operational deadline of Dec 31 2026.