Description
The contract involves the restoration of fish passage and protection of aquatic resources in West Timber Creek and Rose Creek, including the replacement of undersized culverts, reclaiming unused diversions, and reconstructing irrigation diversions. The project requires a mandatory pre-bid meeting and has a bid deposit requirement of 10% of the total bid. The contract was awarded to Wilson Bros Construction and Western Municipal Construction of Wyoming, with a total bid amount of $1,787,420.00 and $1,360,745.00, respectively.
• The project includes replacing six undersized culverts and reclaiming four unused diversions.
• The project requires the installation of a siphon to convey irrigation water and reconstructing one irrigation diversion.
• The contract has a bid alternative for Rose Creek Culvert #3 and #4.
• The project has a total bid amount with alternatives of $2,475,132.00.
• The contract was awarded on September 25, 2025.