This contract concerns the installation and resurfacing of municipal cart‑paths on four specific holes (5, 6, 13, 14) of the Bunker Links Golf Course, with a potential addition of Hole 1 pending a new quote. The work is a short, intensive pavement project expected to be completed in a four‑day window in late October 2026. Four local Illinois contractors submitted bids, with the lowest total bid ($35,460) coming from City Coal & Asphalt, making them the likely awardee. The solicitation was conducted through a full and open competition after an earlier bid round received no submissions.
• Scope: Asphalt cart‑path installation and resurfacing for four (potentially five) golf‑course holes.
• Timeline: Bids due 9/23/2026; work scheduled 10/26‑10/30/2026 (approximately 4 working days).
• Value: Total bid amounts range from $32,775 to $122,850; the low‑bid estimate is about $35,460, indicating a modest‑size contract.