The Airfield Pavement Preservation Project at Elko Regional Airport involves comprehensive pavement maintenance, including crack sealing, asphalt surface treatments, and pavement marking work on runways, taxiways, and general‑aviation aprons. The contract is a single‑award to Maxwell Asphalt, Inc., with a total estimated value of roughly $1.14 million. Bids were received on May 20 2025, and the work must be completed within 35 working days after the Notice‑to‑Proceed, with liquidated damages of $1,000 per day for delays. The solicitation required compliance with prevailing‑wage determinations, DBE participation, and extensive safety and environmental plans. Key elements include:
• Mobilization (capped at 10 % of contract value)
• Joint sealants and emulsified‑asphalt seal‑coat (both 1:1 and 2:1 dilutions)
• Pavement marking removal, temporary and permanent markings, and reflective media installation
• Strict adherence to FAA safety‑phasing requirements and liquidated‑damage penalties.