The City of Galesburg Public Works Department issued a bid for a comprehensive “Miscellaneous Sidewalk Project,” encompassing new Portland cement concrete sidewalks, aggregate base work, removal of existing pavement/curb/brick, installation of detectable warnings, and associated mobilization and traffic‑control services. Three contractors submitted detailed line‑item bids, with total amounts ranging from $88,552.90 (Miller & Son Construction Co.) to $149,024.40 (Brandt Construction Co.) and $100,365.60 (Lockwood Excavating & Construction Inc.). The scope includes both material‑based unit‑price items (e.g., concrete per square foot) and lump‑sum services (e.g., mobilization). No award decision, contract start/end dates, or additional terms are provided, indicating the procurement is still in the evaluation phase.
• Comprehensive sidewalk construction/repair package for the City of Galesburg, IL.
• Three competing bids; lowest bid approx. $88.5 K.
• Scope covers concrete work, demolition, detectable warnings, and traffic control.