Awarded vendors
- Shock Brothers
Description
This contract concerns the removal and replacement of interior flooring in the Engineering Dean’s Office at Wayne State University, including installation of 4½‑inch base molding, coordination of furniture moves, and site logistics such as dumpster provision, lift‑gate provision, and parking fees. The work must be completed on a tight schedule—substantial completion is required by February 1 2024—with liquidated damages of $250 per day for any delay. The solicitation was a mandatory‑pre‑bid, full‑open competition with bids due December 21 2023, and the award was made to Shock Brothers. The project is subject to Wayne State’s prevailing‑wage requirements, certified‑payroll submissions, insurance, bonding, and diversity‑spend reporting.
• Scope: interior flooring replacement, base molding, and related site work for the Dean’s office (first‑floor of the Engineering Building).
• Schedule: pre‑bid conference Dec 14 2023, bid due Dec 21 2023, construction to start after contract execution, substantial completion by Feb 1 2024.
• Compliance: WSU wage rates, certified payroll, 5 % bid bond (if bid ≥ $50K), performance and labor bonds, insurance, diversity reporting, smoke‑free campus.