Awarded vendors
- Q & D Construction
Description
This contract calls for the complete rehabilitation of the air‑carrier apron at Elko Regional Airport, including demolition of existing concrete/asphalt, installation of new asphalt surfacing, concrete flatwork, sidewalks, ramps, joint and crack repairs, pavement markings, and the removal, storage, and re‑installation of perimeter fencing and security gates. The work is divided into three schedules (two federally‑funded rehabilitation packages and one non‑federal package) and must be completed within an 84‑day construction period. The City of Elko issued the solicitation as a sealed‑bid, unit‑price competition; Q & D Construction was ultimately awarded the contract. The project is subject to FAA safety and environmental requirements, Davis‑Bacon prevailing‑wage rules, and a 1.51 % DBE participation goal.
• Scope: apron demolition, asphalt paving, concrete work, markings, fencing, utilities, and related site‑control measures.
• Schedule: 84 calendar days, phased in three distinct stages (35‑day, 28‑day, 21‑day segments).
• Procurement: full open competition, unit‑price bid, award to Q & D Construction, with bid bonds, performance and payment bonds, and liquidated‑damage provisions.