The Debra Drive Retaining Wall project involves the reconstruction of an existing concrete block wall, located along the eastern side of Debra Drive. The project includes wall replacement with a block wall, sidewalk, curb & gutter, and street items. The bid results table lists several bidders, with RCS having the lowest bid at $307,537.48. The project's scope of work includes reconstruction of the existing wall, which is approximately 150 feet in length and 3 to 5 feet high.
• The project is located in Rapid City, South Dakota.
• The bid posting date was October 26, 2024.
• The bid submission date was November 12, 2024.
• The project's advertising authority is $300,000.00.
• The bid results table lists several bidders, with RCS having the lowest bid at $307,537.48.