The U.S. Army Corps of Engineers Louisville District will issue an IFB for a firm‑fixed‑price construction contract to replace the Rough River Lake Axtel Wastewater Treatment Plant. The scope includes complete demolition of the existing plant, removal of perimeter fencing and gravel surfacing, and construction of a new subsurface wastewater treatment and disposal system. Major elements comprise precast concrete pretreatment septic tanks, lift stations, dose stations, a packaged aerobic treatment unit, soil‑drip dispersal field, gravity and pressure sewer piping, full electrical and control systems, site grading, erosion control, and restoration of security fencing. An optional line‑item for rock excavation is also included. This project is a full‑turnkey civil‑construction effort requiring demolition, civil works, mechanical, electrical, and control system integration.
• Demolition and disposal of existing plant and site improvements
• Installation of precast septic tanks, lift stations, and ATU
• Construction of subsurface treatment and soil‑drip dispersal field
• Gravity and pressure sewer piping networks with associated valves
• Complete electrical service, control enclosures, surge protection, and alarm systems
• Site grading, trenching, erosion control, and fence replacement
• Optional unit‑priced rock excavation