The Snowline Joint Unified School District is rebidding the Wrightwood Basketball Court Improvement. The project entails demolishing the existing asphalt surface, grading and compacting the sub‑grade, installing a new 3‑inch asphalt concrete surface over a 4‑inch Class II aggregate base, applying a 30‑day cure, two coats of slurry seal, and final line striping. Red‑wood headers will be installed around the perimeter, and all existing court equipment (posts, backboards, etc.) will be protected. The original concrete alternate option has been removed, so only the asphalt scope is required. The contract is subject to California public‑works rules, including prevailing‑wage requirements, DVBE participation, and mandatory DIR registration for all prime and subcontractors. Bidders must provide a 10 % bid bond and 100 % performance and payment bonds, and meet insurance minimums.
• Remove existing asphalt and dispose of debris.
• Grade, compact, and prepare sub‑grade to ≥ 90 % relative compaction.
• Install 3‑in. asphalt over 4‑in. Class II base, cure 30 days, then slurry seal and line striping.
• Install pressure‑treated redwood perimeter edging; protect existing court equipment.
• Comply with California licensing, DIR registration, prevailing‑wage, DVBE goals, and bonding/insurance requirements.
Attached files
Contact
Andrea Bilodeau(Director of Facilities, Warehouse & Reprographics)
You found this one. Bid Banana has 1.6M+ bids and awards.
You found this bid by looking. Bid Banana searches open government bids across all 50 states, updated daily, so you stop hunting: save a search once and we email you your new matches, daily or weekly.