The City of Ann Arbor is seeking a qualified contractor to remove and replace all concrete elements (sidewalks, ramps, curbs, gutters, pavement, equipment pads, etc.) at the North Terminal Building of the Ann Arbor Airport. The contract will be awarded on a lump‑sum basis, with strict limits on subcontractor and material mark‑ups, and requires a 48‑72 hour emergency response capability. Bidders must attend a mandatory pre‑proposal conference, submit a sealed physical proposal plus a digital copy, and include extensive certifications (prevailing‑wage, living‑wage, non‑discrimination, conflict‑of‑interest, etc.). Evaluation will be point‑based across qualifications, safety, workforce development, social equity, and price.
• Scope: full demolition, disposal, sub‑grade prep, forming, reinforcing, placement, finishing, curing, jointing, sealing, back‑filling, and site restoration for all concrete at the North Terminal.
• Contract type: lump‑sum construction agreement with allowable 5 % subcontractor and 15 % material/equipment mark‑ups; performance and labor‑material bonds required.
• Mandatory requirements: attend pre‑proposal conference (Oct 7), submit bid bond (5 % of bid), provide numerous declarations, and maintain compliance with prevailing‑wage, living‑wage, safety, and non‑discrimination ordinances.
• Timeline: Questions due Oct 15, proposals due Oct 28, evaluation Nov 2026, possible award Dec 2026.