The project calls for the design‑build construction of a new compressed‑natural‑gas (CNG) fueling station in Birmingham, AL. The contractor will execute selective demolition, site grading, utility installation, a 1,750 sf service‑admin building, a canopy with fueling islands, an equipment yard, and all associated mechanical, electrical, and safety systems. The contract is a single‑prime, 365‑day construction effort funded 80 % by a Federal FTA grant and 20 % locally. Bid bonds are limited to 5 % of the estimated cost (capped at $10,000), and the award will be made on a best‑value basis after a technical (60 %) and price (40 %) evaluation.
• Scope includes demolition, civil/structural works, CNG compressors, storage, dispensing equipment, and full commissioning.
• Mandatory certifications: Alabama General Contractor License, Buy‑America, Davis‑Bacon, E‑Verify, DBE/DBR compliance, and extensive insurance/bonding.
• Key dates: RFP posted Oct 6 2026, pre‑proposal conference Oct 22 2026, questions due Nov 5 2026, proposal deadline Nov 19 2026, award expected Dec 17 2026.
• Contractor must provide a 5 % bid bond (max $10,000) and, after award, 100 % performance and payment bonds.
• Project will be overseen by BJCTA’s procurement office, with Volkert, Inc. as program manager and Skanska USA Building as construction manager.