The City of Shawnee is soliciting bids for a 2027 stormwater pipe repair project that involves extensive excavation, pipe replacement, in‑place lining, and associated surface restoration across multiple locations. The contract covers removal and replacement of up to 1,640 linear feet of pipe (15‑54″), replacement of 23 storm structures, and lining of 1,680 linear feet of pipe (15‑42″), plus concrete curbs, sidewalks, inlet tops, street repairs, and landscaping. The work must be completed within roughly 200‑230 days after the Notice to Proceed, with an anticipated start around early March 2027. This opportunity is suitable for contractors experienced in civil construction, water‑utility pipe work, and municipal surface restoration.
• Scope: pipe removal/replacement, structure replacement, in‑place pipe lining, concrete curb/gutter, sidewalk, inlet tops, street repair, sod and other site restoration.
• Scale: up to 1,640 ft of pipe replacement, 1,680 ft of lining, 23 storm structures, 16 primary sites (plus up to 9 alternates).
• Timeline: bid submission by 11/12/2026, anticipated NTP ≈ March 1 2027, 200 days to substantial completion, 230 days to final completion.