The Calhoun City School District seeks a qualified Construction Management (CM) firm to oversee the designâbuild renovation and modification of Calhoun Elementary School and Calhoun Primary School. The CM will act as the prime contractor, develop bid packages, obtain competitive bids, manage the constructionâatârisk contract, and ensure the project is completed within a $5 million Phase 1 budget and by July 21 2027. A mandatory preâproposal conference is required; proposals must be submitted in sealed envelopes by October 19 2026.
⢠Scope includes flooring, ceiling tiles, painting, HVAC replacement, playground upgrades, door replacement, lighting, intercom, lowâvoltage wiring, restroom fixtures, and miscellaneous repairs.
⢠Phase 1 budget: $5,000,000; Phase 2 to be defined later.
⢠CM at Risk contract with overhead & profit percentage plus fixed generalâconditions fee.
⢠Mandatory preâproposal meeting on Sep 29 2026 (attendance required).
⢠Submission deadline: Oct 19 2026, 2:00 PM EST, six hard copies + digital copy.
⢠Required bonds, insurance, and compliance with Georgia publicâworks statutes.
⢠Evaluation based on firm history, experience, personnel, financials, approach, claims history, references, and fee structure.
⢠Project duration approx. 10 months; substantial completion targeted for July 2027.
⢠Primary contact: Dr. Peter Coombe, Assistant Superintendent (email & phone provided).