The City of Corvallis, Oregon, requested bids for the design-build installation of a 100kW ground-mounted solar array at the Corvallis Municipal Airport. The contract includes a turn-key installation of the photovoltaic system, obtaining required permits, and installing monitoring equipment. The selected contractor must demonstrate experience with PV systems and comply with local, state, and federal codes. The contract is subject to ORS 279C.800 to 279C.870. Key aspects of the contract include:
• The installation of a 100kW ground-mounted solar array
• A turn-key installation including all labor and materials
• Compliance with the Blue Sky Grant, Energy Trust of Oregon, and Pacific Power net metering requirements
• Adherence to local, state, and federal codes
• A mandatory pre-bid meeting was held on June 14, 2016
• The contract is a public works contract subject to ORS 279C.800 to 279C.870