This contract calls for the wet demolition of existing structures at 1213 Chinquapin St., Mobile, AL, including removal of all building components, utility capping, site cleanup, and extensive erosion‑control measures. The contractor must also handle lead‑based paint and asbestos waste in accordance with federal and state environmental regulations, obtain all necessary permits, and provide detailed documentation (photos, waste shipment records, lien releases). The award is a stipulated‑sum (lump‑sum) contract awarded through an open RFQ, with a 30‑day performance window after the Notice to Proceed.
• Wet demolition of structures, foundations, and associated debris.
• Utility disconnection/capping (sewer, water, gas) and notification to the Municipal Enforcement Department.
• Full erosion‑ and sediment‑control plan (temporary BMPs and permanent site stabilization).
• Compliance with Lead‑Based Paint, Asbestos, Clean Water Act, and local codes; required documentation and final newspaper notice of completion.