The Wyoming State Construction Department, Procurement, on behalf of the Wyoming Game and Fish Department, issued a Request for Proposal (RFP) for design and professional services in support of the Auburn Fish Hatchery. The project involves producing a complete engineering design and construction documents for the isolation effluent treatment project. The contract was awarded to Sunrise Engineering. Key aspects of the project include a mandatory pre-proposal conference, questions and answers submitted through the Public Purchase website, and a requirement for proposers to register on the website. The project is located in Caribou County, Idaho, in the Caribou-Targhee National Forest.
• The RFP was issued on February 2, 2024, with a submission deadline of March 5, 2024.
• A mandatory pre-proposal conference was held on February 15, 2024, via Google Meets.
• Questions and answers were submitted through the Public Purchase website.
• The contract was awarded to Sunrise Engineering on March 15, 2024.