The Gary Sanitary District is seeking a qualified contractor to provide complete CIPP (Cured‑In‑Place Pipe) lining of approximately 1,075 linear feet of existing 12‑inch sanitary sewer pipe along 2100 West 2nd Avenue, Gary, IN. The work includes removal of roots and encrustations, pre‑liner or chemical grouting of infiltration points, installation of a 0.35‑inch minimum‑thickness CIPP liner extending four inches into each manhole, reinstatement of all active laterals, CCTV inspection before and after installation, provision of a sample liner for engineer review, and full site restoration (driveways, sidewalks, landscaping). The contractor must supply all labor, materials, equipment (including Vactor, CCTV, boiler, and refrigeration trucks), obtain required permits, and comply with local, state, and federal regulations, including erosion‑control and traffic‑management plans. Bids are due by 2:00 p.m. on October 15, 2026, with work to commence upon notice to proceed and be completed within 30 days unless an alternate schedule is submitted.
• CIPP lining of 12‑in. pipe – 1,075 ft total
• Minimum liner thickness 0.35 in., extending 4 in. into manholes
• Pre‑liner/chemical grouting of infiltration points
• CCTV video inspection (pre‑ and post‑work) to NASCCO standards
• Removal of roots, protruding taps, encrustations
• Re‑instatement of all active laterals and site restoration
• Required permits, erosion‑control & traffic‑management plans
• Completion window: 30 days from Notice to Proceed
• Submission: sealed envelope or electronic via OpenGov by Oct 15, 2026