The Central Arizona Water Conservation District (CAWCD) is seeking qualified contractors to perform a complete repair of the KW1A transformer at the Waddell Pumping Plant. The work includes physical separation, gas enclosure, electrical isolation, de‑gassing, and related testing as detailed in the attached technical specifications. A mandatory pre‑proposal conference will be held on September 22, 2026 at the plant site. Proposals are due electronically by October 14, 2026, with contract award expected October 19, 2026 and final deliverables required by December 21, 2026. Evaluation will consider technical compliance, experience, quality‑assurance processes, schedule, warranty, and price. The contractor must meet extensive insurance, OSHA VPP, and safety requirements, and will be responsible for all permits, inspections, and cleanup.
• Scope: Full repair of KW1A transformer (mechanical, electrical, gas handling).
• Mandatory pre‑proposal conference: Sep 22, 2026 (on‑site).
• Proposal deadline: Oct 14, 2026 (electronic).
• Award date: Oct 19, 2026; completion deadline: Dec 21, 2026.
• Evaluation criteria weighted across technical, experience, QA, schedule, and price.
• Required insurance limits and OSHA VPP compliance.
• Primary contact: Kyle Talbert (623‑869‑2409,
[email protected]).