This solicitation seeks qualified contractors who already hold a GDOT Maintenance Master Services Agreement (MSA) to perform drainage rehabilitation, repair, replacement, and related maintenance on State Route 29 in Baldwin County, GA. The work includes capping existing drop‑inlet boxes, removing and replacing arch culverts with 24‑in. reinforced concrete pipe, back‑filling, pavement repair, traffic control, erosion control, and all required testing and permitting. Only pre‑qualified firms may bid, and all required compliance forms (security affidavit, tax compliance, etc.) must be uploaded with the bid package. The contract will be awarded to the lowest responsive and responsible bidder, with performance and payment bonds equal to the contract price. The project must be started within 30 days of the pre‑work meeting and completed within 45 days, with critical construction tasks completed within 14 calendar days after the open cut.
• Eligible bidders: GDOT‑pre‑qualified contractors holding MSA #48400‑410‑000043083.
• Scope: Drainage pipe replacement, drop‑inlet caps, back‑fill, pavement repair, traffic control, erosion & storm‑water compliance on SR‑29 Baldwin (MP 4.64).
• Schedule: Opening 28 Oct 2026, bid deadline 12 Dec 2026; work must be finished within 45 days of start; critical tasks within 14 days after open cut.
• Required documents: GA Security & Immigration Affidavit, Tax Compliance Form, signed ITB package, bonding, and all compliance attachments.