The City of High Point is seeking sealed proposals for the upgrade of the Riverdale Pump Station from a capacity of 30 MGD to 45 MGD. The scope includes demolition of existing structures, installation of new pumps, piping, odor‑control systems, a generator, an electrical building, and comprehensive electrical, instrumentation, and SCADA upgrades. Additional work comprises utility connections, site work, and temporary bypass pumping to ensure uninterrupted wastewater service during construction, followed by startup, testing, and commissioning. Bidders must obtain the contract documents (available for a fee) and may attend a pre‑bid conference for clarification. The bid opening is scheduled for December 2, 2026.
• Upgrade capacity to 45 MGD, replace pumps and major mechanical/electrical systems
• Demolition, civil work, odor control, generator, electrical building, SCADA, instrumentation
• Temporary bypass pumping to maintain service during construction
• Required performance and payment bonds equal to 100 % of contract price
• Pre‑bid conference 10/28/2026, 11 AM at Eastside Wastewater Treatment Plant (attendance urged)
• Sealed bids due 12/2/2026, 2 PM; public bid opening at Municipal Operations Center, High Point, NC