The City of Worcester is procuring septic‑truck services for a one‑year period, covering sewage pump‑and‑haul operations and standby call support. The contract will be awarded to the lowest responsive bidder and may be extended up to two additional years at the City’s discretion. The work includes moving up to 75,000 gallons within the sanitary system, 25,000 gallons to a treatment facility, and providing 20 hours of standby service.
• Scope: Pump‑and‑haul (75k gal internal, 25k gal to UBWPAD) plus 20 hrs of standby calls.
• Duration: 12 months (Nov 2024 – Oct 2025) with up to two one‑year renewal options.
• Award: Jeff D. Helgerson Excavating, Inc. at $17,600 (lowest net price).
• Requirements: Minimum 5 years septic‑hauling experience, 1,500‑gal vacuum truck, insurance (GL $1M/$2M), response times (24 h normal, 2 h emergency).