The USDA Forest Service is soliciting a firm‑fixed‑price contract to develop and operate the Champion Creek rock‑crushing pit on the Sawtooth National Recreation Area, Idaho. The work includes site preparation, crushing and processing of aggregate, stockpiling up to 27,500 cubic yards, and site restoration, all performed under strict environmental, safety, and fire‑prevention requirements.
• Site work: clearing, grubbing, topsoil stripping, over‑burden removal, construction of access roads, and pit development.
• Aggregate production: crushing to sub‑base, base, and surface‑course specifications, with a base quantity of 20,000 CY and an optional 7,500 CY.
• Compliance: mandatory performance and payment bonds, DEI certifications, hazardous‑spill and fire‑prevention plans, and adherence to FP‑14 supplemental specifications.
• Timeline: bids due 5 Nov 2026, award expected 16 Nov 2026, performance period 3 May 2027 – 30 Jun 2027 (58 days).